How to calculate the area of a gable or hip roof

You work out the area of a roof as the roof plan (eaves included) divided by the cosine of the pitch: a 14.25 × 8.65 m gable roof pitched at 42° has about 166 m². A hip roof over the same plan and at the same pitch has the same number of square metres, but needs more covering for the cuts: about 12% instead of about 5%.

In this article

  1. 1How to calculate it
  2. 2Waste
  3. 3Example: a 14.15 × 8.44 m house with a 42° roof
  4. 4What it costs
  5. 5Work it out in Baukit
  6. 6Frequently asked questions
Open in Baukit→
AnswerYou work out the area of a roof as the roof plan (eaves included) divided by the cosine of the pitch: a 14.25 × 8.65 m gable roof pitched at 42° has about 166 m².
The YouTube player (youtube-nocookie.com) loads only after you click.

01How to calculate it

The simplest formula works for any roof whose slopes all have the same pitch:

roof area = area of the roof plan ÷ cos(pitch)

plan 14.25 × 8.65 m123.26 m²cos 42°÷0.743roof=165.87 m²
The roof plan with the eaves divided by the cosine of the pitch. It works for any roof whose slopes all have the same pitch.

The roof plan is the rectangle (or other shape) set by the eaves and the edges of the roof, not by the walls. That is why you add the overhangs on both sides to the dimensions of the house.

The example roof in plan
ridgeslope 82.94 m²slope 82.94 m²14.25 m8.65 m14.15 m (walls)8.44 m
  • ridge 14.25 m
  • eaves 2 × 14.25 = 28.5 m
  • verges 4 × 5.82 = 23.28 m
  • walls 14.15 × 8.44 m
The roof plan is set by the eaves, not the walls: 14.25 × 8.65 m instead of 14.15 × 8.44 m. The arrows show the fall of each slope. The 5 and 10.5 cm overhangs are almost invisible in the drawing, but over the whole roof they add about 3.8 m² of plan.

For a gable roof you can also work it out directly:

gable roof area = 2 × eaves length × slope length

slope length = half the width of the plan ÷ cos(pitch)

The example roof in section
42°ridgeeaves5.82 m4.325 m8.65 m
half the plan4.325 mcos 42°÷0.743slope length=5.82 m
The slope is longer than half the plan: you divide by the cosine of the pitch. The steeper the roof, the smaller the cosine and the more roof over the same plan.

The slope length is the distance from the eaves to the ridge measured along the roof. Useful values:

Roof pitchcosMultiplier 1 ÷ cos
30°0.8661.155
35°0.8191.221
40°0.7661.305
42°0.7431.346
45°0.7071.414

With a 45° roof, every square metre of plan therefore gives about 1.41 m² of roof.

Work out your roof
Roof plan length
m
Roof plan width
m
Pitch42°
Roof
Roof area165.87m²14.25 × 8.65 = 123.26 m² ÷ cos 42° (0.743) = 165.87 m²
Slope length
5.82 m
Covering +5%
174.2 m²
Membrane +10%
182.5 m² · 3 rolls
Ridge
14.25 m
Eaves
28.5 m
Verges
23.28 m
pitch42°slope length5.82 mplan width8.65 m
The roof plan is the dimensions including the eaves. The formula works when all slopes have the same pitch. A hip roof has the same area but a shorter ridge, hips, eaves all round and more covering waste.

For your order you also need the lengths of the edges: the ridge (ridge caps), the eaves (eaves flashing, gutters), the verges (verge trims), and the hips and valleys on roofs with more slopes. Dormers and slopes at a different pitch are worked out as separate slopes.

An L- or T-shaped roof is worked out the same way if all its slopes have the same pitch: divide the roof plan into rectangles, add up their areas and divide the sum by the cosine of the pitch. Where the two wings meet, valleys form. You need their length for the flashings, and the cuts along the valleys raise the covering waste. When the slopes have different pitches (for example a dormer or a canopy over the entrance), work out each one separately with its own pitch.

An L-shaped roof (diagram)
ABridgevalleyhip
roof planA + Bsame pitch÷cos α=roof area
You split the plan into rectangles A and B, add up their areas and divide by the cosine of the common pitch. The valley in the inside corner raises the covering waste and needs flashing.

Battens and counter-battens are counted in metres. Counter-battens run along the rafters, so their length is the number of rafters × the slope length. Battens run horizontally, at a spacing that depends on the covering: for metal roof tiles it is the module length, and for tiles it is the spacing in the manufacturer's instructions. The number of batten rows on a slope is the slope length ÷ the batten spacing + 1, and each row is as long as the eaves.

The most common mistakes are working from the plan of the walls without the eaves, and multiplying by the pitch "by eye". You can read how many sheets of metal roof tiles to order in how much metal roof tiling for a roof, and work out the roof drainage in how many gutters and downpipes for a house.

02Waste

RoofWaste in BaukitWhy
Without hips or valleys (gable, mono-pitch)5%Cuts only at the gables and the ridge
With hips or valleys (hip, multi-slope, L- or T-shaped)12%Diagonal cuts along the hips and valleys
Roofing membrane10%Laps of about 10–15 cm between strips

Baukit adds the same waste to every covering: metal sheeting, metal roof tiles and tiles. The waste values are roofers' practice. On a roof with many valleys, dormers and short slopes there can be more cutting, and manufacturers of modular metal roof tiles give the number of sheets from a cutting plan of the slopes. When you order the covering, ask for a cutting plan and compare it with the quantity from Baukit.

03Example: a 14.15 × 8.44 m house with a 42° roof

The assumptions follow the free „PS.Arch 150” design from the catalogue of GUNB, the Polish building control authority: a house measuring 14.15 × 8.44 m over the insulation, a 42° gable roof, eaves overhangs of 10.5 cm on the long walls and 5 cm at the gables. The 10.5 cm overhang follows from the rafter length in the bill of quantities (5.82 m); the design drawing gives 10 cm. The example in Baukit has the same data.

  1. Roof plan. Length: 14.15 + 2 × 0.05 = 14.25 m. Width: 8.44 + 2 × 0.105 = 8.65 m. Plan: 14.25 × 8.65 = 123.26 m².
  2. Slope length. 8.65 ÷ 2 = 4.325 m, and 4.325 ÷ 0.743 = 5.82 m.
  3. Roof area. 2 × 14.25 × 5.82 = 165.87 m². The plan gives the same: 123.26 ÷ 0.743 = 165.87 m².
  4. Covering with 5% waste. 165.87 × 1.05 = 174.2 m² of metal sheeting or metal roof tiles.
  5. Membrane with 10% waste. 165.87 × 1.10 = 182.5 m², or 3 rolls of 75 m².
  6. Edges. Ridge 14.25 m, or 8 ridge caps of 2 m. Eaves 2 × 14.25 = 28.5 m. Verges 4 × 5.82 = 23.28 m, or 12 verge trims of 2 m.
  7. Gutters and downpipes. Gutters along both eaves: 28.5 m, or 8 gutters of 4 m. Each metre of gutter takes 2 brackets: 28.5 × 2 = 57 brackets. Downpipes: one on each side, from eaves at about 4 m down to the ground, so 2 × 4 m = 8 m, in lengths of 3 m: 4 lengths, plus bends and pipe clips as the system's instructions say.
To buy for the example roof
  • Covering174.2 m²165.87 m² + 5% waste
  • Roofing membrane3rolls of 75 m² (182.5 m²)
  • Ridge caps 2 m8for a 14.25 m ridge
  • Verge trims 2 m12verges 4 × 5.82 m
  • Gutters 4 m8eaves 28.5 m
  • Gutter brackets5025 for each gutter run
  • Downpipes 3 m42 × 4 m, plus bends and brackets
Quantities from the example above: a 42° gable roof, metal roof tiles with 5% waste. The manufacturer gives the number of metal sheets from the slope cutting plan.

A hip roof for comparison. Over the same 14.25 × 8.65 m plan and at 42°, a hip roof also has 165.87 m². The edges change: the ridge shortens to 14.25 − 8.65 = 5.60 m, four hips of about 7.25 m each are added (29.0 m in total), and the eaves run all round: 2 × (14.25 + 8.65) = 45.8 m. The covering with 12% waste is 185.8 m², about 12 m² more than for the gable roof.

Same plan, same pitch: gable and hip
165.87 m²165.87 m²Gableridge 14.25 m · verges 4 × 5.82 meaves 28.5 mHipridge 5.60 m · hips 4 × 7.25 meaves 45.8 m
  • ridge
  • eaves
  • verges
  • hips
Covering with waste
  • Gable, 5% waste174.2 m²
  • Hip, 12% waste185.8 m²
Both roofs have an area of 165.87 m². The hip roof has a shorter ridge, four hips and eaves all round, and the diagonal cuts raise the covering waste to about 12%.

The bill of quantities for „PS.Arch 150” gives 165.87 m² of covering and membrane. From a drawn model of this house (10 cm overhangs, a 14.25 × 8.64 m plan), Baukit works out 165.67 m² of roof, a difference of about 0.1%.

04What it costs

Indicative gross prices as of October 2026
MaterialTypical priceRangeShops
Modular metal roof tile sheet 0.5 mm (polyester)Pack: m² (sheets cut to size)no current price
Interlocking clay roof tile, price per m² of roof (approx. 10–15 pcs/m²)Pack: piece ≈ 0.09 m² (approx. 11 pcs/m²)106.05 PLN/m²90.51–130.43 · 3 shops90.51–130.433 shops
Highly vapour-permeable roof membrane approx. 150 g/m²Pack: roll 1.5×50 m3.74 PLN/m²approx. 281 PLN per pack3.71–5.50 · 3 shops3.71–5.503 shops
Roof batten 40×50 mm, impregnated, price per mPack: running metre (battens 3–5 m, sold by the metre)3.95 PLN/m3.40–4.50 · 2 shops3.40–4.502 shops
Ridge cap for metal roof tiles, 2 mPack: 2 m pieceno current price
Roofing screws 4.8×35 for metal sheet, 250 pcsPack: pack of 2500.18 PLN/pcapprox. 44 PLN per pack0.14–0.22 · 3 shops0.14–0.223 shops
PVC gutter 125 mm, 4 mPack: 4 m piece (also 3 m)14.66 PLN/mapprox. 59 PLN per pack12.73–17.23 · 3 shops12.73–17.233 shops
Long metal gutter hook (rafter-mounted) for 125 mm PVC gutterPack: piece16.17 PLN/pc15.95–16.40 · 2 shops15.95–16.402 shops
PVC downpipe 90 mm, 3 mPack: 3 m piece18.83 PLN/mapprox. 56 PLN per pack18.00–23.41 · 3 shops18.00–23.413 shops
Prices in Polish złoty (zł) from Polish building shops: the median of current offers from at least two shops, VAT included. Shop prices vary; check before you buy.

The prices in the table are the median of offers from several Polish shops, including VAT, with a date. Manufacturers usually price metal sheeting and metal roof tiles individually, from a cutting plan of the roof, so treat those as a guide. Labour and the roof structure are not in the table.

05Work it out in Baukit

Open in Baukit→
  1. Click „Open in Baukit”. A 14.15 × 8.44 m house opens with a 42° gable roof and the notebook open.
  2. Select the roof. The notebook shows the roof area, the covering with waste, the membrane, the ridge caps, the verge trims and the gutters.
  3. Change the pitch or the eaves in the panel on the right and see the new area.
  4. Change the roof to a hip roof: hips are added, the ridge gets shorter and the covering waste goes up.
  5. Hover over a row in the notebook to highlight the edges on the plan. You open the notebook with the „Notebook” button in the bottom left-hand corner or the 4 key.
The example roof in Baukit
baukitPlan3DData
ridgeslope 82.94 m²slope 82.94 m²14.25 m8.65 m14.15 m (walls)8.44 m
Roof
Roof area165.87 m²
Covering174.2 m²+5%
Membrane182.5 m²
Ridge caps8 pcs
Verge trims12 pcs
Gutters28.5 m
Shape
Pitch42°
Eaves overhang10.5 cm
The selected roof and its data: roof area, covering with waste, membrane, ridge caps, verge trims and gutters. You change the pitch and the eaves in the panel on the right.

The same model also works out the mineral wool for the attic and the usable floor area under the slopes.

06Frequently asked questions

How do I work out the roof area from the plan?+

Work out the area of the roof plan including the eaves and divide it by the cosine of the pitch. For a 35° roof you divide by 0.819, which is the same as multiplying by about 1.22. This works for a roof whose slopes all have the same pitch.

Does a hip roof have a larger area than a gable roof?+

Not over the same plan and at the same pitch: both areas equal the plan divided by the cosine of the pitch. A hip roof costs more because it has longer eaves, hips to finish and more cutting of the covering.

How many roof tiles per 1 m² of roof?+

Usually about 10 to 15 per square metre, depending on the model and the batten spacing. The tile manufacturer gives the exact number. On top of that come verge tiles, ridge tiles and waste for the cuts.

Are roof windows deducted from the roof area?+

Usually not for ordering the covering, because you have to cut sheets or tiles around the window anyway. You deduct the windows for the mineral wool and the plasterboard on the inside. In „Wariant I”, eight roof windows take up about 8.7 m² of the roof.

How many gutters does a house need?+

Gutters run along the eaves, so their length is the sum of the eaves that the water runs off. For a 14.25 m gable roof that is 2 × 14.25 = 28.5 m of gutter, or 8 lengths of 4 m, and usually one downpipe on each side. The details are in how many gutters and downpipes for a house.

Related

  • Loft insulationHow much mineral wool for an attic
  • Usable floor areaUsable floor area of a house with an attic
Coming soon to the guide
  • How much metal roof tiling for a 150 m² roof? Sheets or modules
  • How many gutters and downpipes for a house? 125 or 150 mm gutters
Sources and method4 sourcesShowHide
  1. Covering waste by roof shape and membrane laps: recommendations from covering and membrane manufacturers, roofers' practice (not checked).
  2. Number of tiles per m²: tile manufacturers' technical data sheets (not checked).
  3. „PS.Arch 150”, przedmiar robót budowlanych, by PS.Arch Piotr Świątkiewicz, 20 November 2023; Główny Urząd Nadzoru Budowlanego, catalogue of free house designs, published 15 December 2023 (in the downloads as „Wariant I”) (in Polish): membrane and covering 14.25 × 5.82 × 2 = 165.87 m², gutters 28.5 m.
  4. Roof area of „PS.Arch 150” from the model: Baukit's calculation, 11 October 2026.
baukit

A free tool to design a house and count its materials.

Product

  • Editor
  • Ready-made houses
  • Film about Baukit

Learn

  • Guide
  • Calculators
  • YouTube

baukit

  • About
  • Contact
  • Terms of service
  • Privacy policy

© 2026 Baukit