Concrete for 100 m² house foundations: formula and example

The strip footings of a 10 × 10 m house (60 × 40 cm footings under the external walls and one 50 × 40 cm internal footing) take about 11.5 m³ of concrete, and with 5% waste you order 12.5 m³, which is two truckloads. The footing cross-section in the design changes the result most: an 80 × 40 cm footing instead of a 60 × 40 cm one takes a third more concrete.

In this article

  1. 1How to calculate it
  2. 2Waste
  3. 3Example: footings for a 10 × 10 m house
  4. 4All the concrete in a house
  5. 5What it costs
  6. 6Work it out in Baukit
  7. 7Frequently asked questions
Open in Baukit→
AnswerThe strip footings of a 10 × 10 m house (60 × 40 cm footings under the external walls and one 50 × 40 cm internal footing) take about 11.5 m³ of concrete, and with 5% waste you order 12.5 m³, which is two truckloads.
The YouTube player (youtube-nocookie.com) loads only after you click.

01How to calculate it

The volume of concrete is always length × width × height, worked out separately for each element:

footing volume [m³] = footing length × footing width × footing height

order [m³] = volume × (1 + waste), rounded up to 0.5 m³

outer strips9.60 m³inner strip+1.88 m³total=11.48 m³waste 5%×1.05with waste=12.05 m³up to 0.5 m³→12.5 m³
Work out each element separately, add them up, add the waste allowance and only then round the result up to 0.5 m³.

Measure the length of the external footings along the footing's axis, which is usually the axis of the foundation wall. Measured this way, the corners come out exactly: at each corner, the piece counted twice on the inside balances the piece left out on the outside. For a rectangular house it is simply the perimeter measured on the axes.

A footing corner, enlarged
0.60 mleft out: 0.30 × 0.30 mcounted twice: 0.30 × 0.30 mfooting axis: measure the length along it
Measuring on the axis, you leave out the orange square outside the corner but count the blue one inside twice: once with each strip. Both are 0.30 × 0.30 m, so the result is exact.

Measure the length of the internal footings between the inner edges of the external footings. If you measured them on the axis all the way to the external footing, you would count the piece where they cross a second time.

The example house's footings, plan
10.00 m on the axis10.00 m9.40 mtotal11.48 m³
  • outer strips 60 × 40 cm: 40.00 m, 9.60 m³
  • inner strip 50 × 40 cm: 9.40 m, 1.88 m³
  • wall axes
Measure the outer strips on the axis (dashed orange line): 4 × 10.00 = 40.00 m. Measure the inner strip only between their inner edges: 10.00 − 0.30 − 0.30 = 9.40 m.

Take the width and height from the structural design. Typical footings of a detached house are 50–80 cm wide and 30–40 cm high. The structural engineer sizes them for the ground and the weight of the house, so don't guess them on site.

Pad footings (under columns) are worked out the same way: length × width × height of each pad. Lean concrete (blinding) under the footings is usually a layer of about 10 cm as wide as the footing.

Section through an outer footing
40 cm10 cm60 cmfoundation wallfooting 60 × 40 cmreinforcement as designedlean concrete approx. 10 cm
A 60 × 40 cm strip footing on a layer of lean concrete about 10 cm thick and just as wide. The structural design specifies the reinforcement and the concrete class; the drawing only marks them.

Foundation walls built from concrete blocks use no ready-mix concrete, but walls cast in formwork do. Then you work them out like footings: length on the axis × wall thickness × height, measuring the internal walls between the faces of the external walls. With block walls, the blocks are the main item: you can work them out in the article how many blocks for a house.

The concrete class also comes from the design. The class is the concrete's strength grade under the European standard: C20/25, for example, is stronger than C16/20. For footings, designers usually specify C16/20 or C20/25, and for floor slabs and ring beams C20/25 or C25/30. You order each class separately, so work out the volumes separately for each class.

Floor slabs are worked out differently, because a beam-and-block floor (such as Teriva) is not a solid slab: read more in the article how much concrete for a Teriva, solid and Ackermann floor. How to order concrete by the truckload is covered in the article how many truckloads of concrete to order.

02Waste

ElementWasteWhy
Footings in formwork3–5%Losses at the pump and in the pipes, filling uneven spots
Footings cast straight into the trenchfrom 5% to 10%The trench sides are uneven and usually wider than the footing
Floor slab, ring beam3–5%Formwork deflection, leftovers in the pump
Lean concreteabout 10%Uneven trench bottom

These values are site practice. You round the waste together with the order: concrete plants usually take orders in steps of 0.5 m³.

03Example: footings for a 10 × 10 m house

Assumptions: a house on a 10 × 10 m plan measured on the axes of the external walls. External footings 60 × 40 cm, one internal footing 50 × 40 cm across the middle of the house, 10 cm of lean concrete under the footings. C20/25 concrete, 5% waste, a 8 m³ truck. The example in Baukit uses the same data.

  1. External footings. Length on the axis: 4 × 10.00 = 40.00 m. Volume: 40.00 × 0.60 × 0.40 = 9.60 m³.
  2. Internal footing. Length between the external footings: 10.00 − 0.30 − 0.30 = 9.40 m. Volume: 9.40 × 0.50 × 0.40 = 1.88 m³.
  3. Total. 9.60 + 1.88 = 11.48 m³.
  4. 5% waste. 11.48 × 1.05 = 12.05 m³.
  5. Order. Up to the next 0.5 m³: 12.5 m³. That is two truckloads: one full (8 m³) and a second with 4.5 m³.
  6. Lean concrete. (40.00 × 0.60 + 9.40 × 0.50) × 0.10 = 2.87 m³. With 10% waste: 3.16 m³, so an order of 3.5 m³ of C8/10 concrete.
Work out your house's footings
House width (axis)
m
House length (axis)
m
Footing width
cm
Footing height
cm
Waste
Concrete to order12.5m³9.60 + 1.88 = 11.48 m³ × 1.05 = 12.05 m³ → up to 0.5 m³
truck 18.0 m³
truck 24.5 m³
Outer strips
9.60 m³
Inner strip 9.40 m
1.88 m³
Trucks of 8 m³
2
Lean concrete 10 cm
3.5 m³
Outer strips measured on the axis (perimeter × width × height), one 50 cm inner strip across the middle of the house, between the faces of the outer strips. Lean concrete with 10% waste. Baukit adds pad footings, cast walls and other inner strips from the drawing.

If the design specified 80 × 40 cm external footings, the external footings alone would take 40.00 × 0.80 × 0.40 = 12.80 m³, which is 3.20 m³ (a third) more.

40.00 m of outer strips: two cross-sections
  • 60 × 40 cm (example)9.60 m³
  • 80 × 40 cm12.80 m³3.20 m³ more
A footing 20 cm wider takes a third more concrete. That is why you always take the cross-section from the design, not from the example.

A real house for comparison. In the free “PS.Arch 150” design from the catalogue of GUNB, the Polish building control authority (a house with an attic storey, 14.15 × 8.44 m), the footings are 80 × 40 cm, and the bill of quantities gives about 17.1 m³ of concrete for the footings together with two pad footings, plus 5.5 m³ of lean concrete. From a drawn model of this house, Baukit works out 16.8 m³ of footings and pads.

04All the concrete in a house

Foundations are only part of the concrete. This is the concrete in “Wariant I” (Variant I) as Baukit works it out from the house model (without waste):

ElementVolumeNotes
Strip and pad footings16.8 m³80 × 40 cm footings, two pads under columns
Floor slab over the ground floor18.2 m³18 cm slab, about 101 m² after deducting the stair opening
Concrete base under the ground floor9.9 m³10 cm layer, about 99 m²
Lintels, ring beams and main beam4.6 m³18 beams, about 60 m in total
Columns1.9 m³24 reinforced concrete columns in the walls
Totalabout 51 m³about 6–7 truckloads, in several deliveries
Concrete in the „Wariant I” house, by element
  • Floor slab over the ground floor18.2 m³
  • Strip and pad footings16.8 m³
  • Sub-floor concrete base9.9 m³
  • Lintels, ring beams, main beam4.6 m³
  • Columns1.9 m³
The footings are less than a third of the house's concrete. You order each element separately, at its own time and in its own class.

Baukit adds up the concrete of each class across the whole house and only rounds that sum up to 0.5 m³. On site, each element is usually cast on a different day, and the concrete plant rounds each delivery separately, so several deliveries come to a little more concrete than this sum. The floor slab and ring beams are usually cast together, in one delivery.

05What it costs

Indicative gross prices as of October 2026
MaterialTypical priceRangeShops
Ready-mix concrete C8/10 (lean concrete, truck-mixer delivery)Pack: ordered in 0.5 m³ steps (truck mixer 8–9 m³)estimate 300–360 PLN/m³average of 5 market sources, incl. kb.pl, as of July 2025, incl. 8% VAT
Ready-mix concrete C16/20 (truck-mixer delivery)Pack: ordered in 0.5 m³ steps (truck mixer 8–9 m³)estimate 360–420 PLN/m³average of 6 market sources, incl. kb.pl, as of July 2025, incl. 8% VAT
Ready-mix concrete C20/25 (truck-mixer delivery)Pack: ordered in 0.5 m³ steps (truck mixer 8–9 m³)estimate 380–450 PLN/m³average of 6 market sources, incl. kb.pl, as of July 2025, incl. 8% VAT
Ready-mix concrete C25/30 (truck-mixer delivery)Pack: ordered in 0.5 m³ steps (truck mixer 8–9 m³)estimate 410–470 PLN/m³average of 6 market sources, incl. kb.pl, as of July 2025, incl. 8% VAT
Portland cement CEM II 32.5R, 25 kg bagPack: 25 kg bag0.72 PLN/kgapprox. 18 PLN per pack0.72–0.73 · 3 shops0.72–0.733 shops
Prices in Polish złoty (zł) from Polish building shops: the median of current offers from at least two shops, VAT included. Shop prices vary; check before you buy. An estimate is a range from market reports and price lists, not a median of shop offers.

The price of ready-mix concrete depends on the region and on the distance from the concrete plant, so for each class the table shows an estimate: the average range of rates from several sources (a market report, concrete plants' and brokers' price lists), dated by the oldest of them. On top of the concrete price, add transport beyond the base distance and a pump if the truck cannot get to the trench: they are not in the table, because they are services, not materials.

06Work it out in Baukit

Open in Baukit→
  1. Click “Open in Baukit”. A 10 × 10 m house opens with strip footings and the notebook open.
  2. Select the footings. The notebook shows the concrete volume in m³ and the order with waste. It does not show the number of truckloads: divide the order by 8 m³, which is what one truck holds.
  3. Change the footing's width or height in the panel on the right and see the new volume.
  4. Press Esc so that nothing is selected: you will see the concrete for the whole house, split into footings, floor slabs, ring beams and columns.
  5. Open the notebook with the “Notebook” button in the bottom left corner or with the 4 key.
The example's footings in Baukit
baukitPlan3DData
10.00 m on the axis10.00 m9.40 mtotal11.48 m³
Concrete C20/25
Strip footings11.48 m³
Order12.5 m³+5%
Footing
Width60 cm
Height40 cm
The footings selected, with the Data view: the volume and the order with waste. You change the footing's width and height in the panel on the right.

The same model also works out the blocks for the foundation walls, the walls of the house and the roof.

07Frequently asked questions

How much concrete for the foundations of a 100 m² house?+

It depends on the footing cross-section and on the number of load-bearing walls. A 10 × 10 m house with 60 × 40 cm footings under the external walls and one internal footing needs about 11.5 m³ of concrete, or 12.5 m³ with waste. With 80 × 40 cm footings it already comes to about 14–15 m³.

How much concrete for a Teriva floor?+

A Teriva floor uses much less concrete than a solid slab of the same thickness, because hollow blocks fill most of the cross-section. According to the manufacturers' instructions, a Teriva 4.0/1 floor (24 cm) uses about 4.7–6.1 m³ of concrete per 100 m², and Teriva 6.0 and 8.0 floors (34 cm) about 12 m³ per 100 m². A 17 cm solid slab takes about 17 m³ per 100 m². On top of that come the ring beams and the infill at the ends of the beams. The floor manufacturer gives the exact consumption.

What concrete class for foundations?+

The structural design gives the class, and that is the one to stick to when you order. In detached houses, footings are usually C16/20 or C20/25. Weaker concrete “because it's only the foundation” is a false economy.

How many bags of cement for 1 m³ of concrete?+

If you mix the concrete yourself, 1 m³ of roughly C16/20 concrete usually takes about 300–350 kg of cement, which is 12–14 bags of 25 kg, plus aggregate and water. For a dozen or more cubic metres, though, ready-mix concrete is more reliable and usually cheaper in labour.

How many m³ of concrete does a truck hold?+

A typical truck mixer carries 6–9 m³ of concrete. When you order, give the volume with waste, rounded to 0.5 m³, and ask the concrete plant about the surcharge for a part load.

Related

  • Blocks and mortarHow many blocks for a house
  • Roof covering and guttersHow to calculate the area of a roof
Coming soon to the guide
  • How many m³ of concrete for a Teriva, solid and Ackermann floor
  • How many truckloads of concrete to order? Class, waste and losses
Sources and method5 sourcesShowHide
  1. Footing cross-sections, concrete classes and the thickness of lean concrete: typical values from detached-house designs; in every case the structural design decides (to be checked by a structural engineer).
  2. Concrete waste and the 0.5 m³ order step: site practice and concrete plants' terms (not checked).
  3. Concrete consumption in Teriva floors: instructions for contractors from Konbet (Teriva 24/60: 0.061 m³/m², 34/45: 0.119 m³/m²) and Betomex (Teriva 4.0/1: 0.0465 m³/m²), read on 13 October 2026 (in Polish).
  4. “PS.Arch 150”, przedmiar robót budowlanych (bill of quantities), author: PS.Arch Piotr Świątkiewicz, 20 November 2023; Główny Urząd Nadzoru Budowlanego, katalog bezpłatnych projektów domów (in Polish), published 15 December 2023 (in the downloads as “Wariant I”): footings, pads and the concrete base.
  5. Footing and pad volume of “PS.Arch 150” from the model: Baukit calculation, 11 October 2026.
baukit

A free tool to design a house and count its materials.

Product

  • Editor
  • Ready-made houses
  • Film about Baukit

Learn

  • Guide
  • Calculators
  • YouTube

baukit

  • About
  • Contact
  • Terms of service
  • Privacy policy

© 2026 Baukit